Project Office
Steve Taylor, Project Coordinator
907-459-1074
Luke Kline, Project Coordinator
907-459-1099
Master Plan
The Isberg Recreation Area Master Plan
was approved by the FNSB Assembly on the evening of December
13, 2007. You can view the Plan by clicking on the links
below:
Isberg Recreation Area Narrative
The Master Plan outlines FNSB's plan for the future development and use of the Isberg Recreation Area. We'd like to offer a special thanks to those of you who took the time to participate in this planning process.
Development Underway
In 2009, the Isberg Recreation Area saw several improvements. For ease of reference, the following update is provided by development activity:
100-Mile Loop Trail Hardening Project:
-
DNR Grant - In December 2008, FNSB Parks and Recreation received a $50,000 Recreational Trails Grant from the Department of Natural Resources, Division of Parks and Outdoor Recreation to "harden" boggy and braided sections of the 100-Mile Loop Trail.
-
FNSB Matching Grant - In April 2009, the Borough Assembly approved an additional $12,500 in matching funds for the project.
Trail Progress Report:
-
Volunteer Efforts by the Bureau of Land Management's Chena Hotshots - In May 2009, while the Chena Hotshots were preparing for the impending fire season, they volunteered many hours harvesting local spruce trees for the "rims" of the state-of-the-art, "burrito" trail hardening technique used in Isberg. They did a great job of harvesting timbers far enough off the trail to preserve the natural feel of the trail corridor, too. Thanks gentleman!
-
Volunteer Work Party - On August 29th, seven volunteers and neighbors joined forces with Parks and Recreation staff to begin hardening the 100-Mile Loop Trail. Thanks to their hard work, we were able to improve approximately 400 feet of trail and construct 50 feet of the first "burrito." We'd like to say a special thank you to the neighbors and trail enthusiasts whom labored so diligently that day. Thanks for your trail assistance!
-
Fall Work by Parks and Recreation Staff - In late September, Parks and Recreation staff continued the work that our volunteers began. Until the snow flew, they placed geo-textile fabric and gravel along additional sections of the 100-Mile Loop Trail and constructed several more "burritos" in the boggier trail sections. The staff improved over 3,200 feet of trail, and plans on completing the project by September 2010.
-
Networking - Thanks to temporary loans of trail-building equipment by the Alaska Department of Natural Resources, the National Park Services, and the Bureau of Land Management, the trail hardening project progressed rapidly. The cooperative efforts of our fellow agencies and trail builders was vital our recent success.
BLM Chena Hotshots
Neighbors volunteering at 100-Mile Loop Trail Work Party
Boggy,
braided trail section before.
Same trail section after "burrito" placement.
Wetlands Permitting:
-
Wetlands Permit Application Phase 1a - In September 2009, Parks and Recreation submitted a Wetlands Permit Application to the Army Corps of Engineers to include the development of the Isberg Recreation Area's 100-Mile Loop Trail, two interpretative boardwalks, and two parking lots. Due to changes to the federal rules regarding "Compensatory Mitigation for Losses of Aquatic Resources," and because of the complexity of the new ruling and its required compensatory mitigation, Parks and Recreation felt that it would be in the community's best interest to reduce the scope of the wetlands permit for the time being and focus on the 100-Mile Loop Trail hardening only. The Isberg Recreation Area Phase 1a project received the Wetlands Permit on October 31, 2008.
-
Wetlands Permit Application Phase 1b - Following a thorough study of the new federal ruling and our compensatory mitigation options, Parks and Recreation submitted a second Wetlands Permit Application to the Army Corps of Engineers on June 3, 2009. The permit application covered the construction for the two interpretive boardwalks and the two parking lots. To ensure that the "compensatory" wetlands are preserved in perpetuity and to preserve the rustic nature of this area of the park, a 7.84-acre Conservation Easement was established at the center of the recreation area. The Isberg Recreation Area Phase 1b project received the second Wetlands Permit on September 17, 2009. To see the location of the Conservation Easement, click here.
Isberg Conservation Area Perimeter Marker.
Parking Lot at Oboe Court:
In September 2009, work began on the parking lot at Oboe Court. The area was hydro-axed and is now ready for construction in the spring of 2010.
Please note: The piles of gravel located in the parking area, at this time, are not part of the parking lot construction. The piles are being staged here in preparation for the continuation of the 100-Mile Loop Trail Hardening project in Spring 2010.
Upland Trails:
Work began this fall with scouting of a new, non-motorized trail in the uplands on the southwest side of the Isberg Recreation Area. Parks and Recreation, with the assistance of neighboring residents, hopes to continue the work this winter. Thanks to those of you that have helped so far!
Hoe Down Way Winter Trail:
A new winter trail was brushed inside the Hoe Down Way right-of-way in November 2009. The historical Girl Scout trail along the north/south power line is used often by the community, however, its approach to Isberg Road presents a safety hazard to snowmachiners - especially young, inexperienced snowmachine drivers. Parks and Recreation felt it was time to set the intended-and more gently sloping-trail access through the established right-of-way, to increase community safety.
Click on the map below to see the location of the new winter trail.
If you are interested in receiving further information on the development of the Isberg Recreation Area, or wish to discuss the project with staff from Parks and Recreation, please contact Steve Taylor at 459-1074, or email staylor@fnsb.us to be added to the project's email distribution list.



