After you receive your Floodplain Permit and your project has been completed, you will submit a certificate of compliance application along with the required documentation certifying that your development complies with applicable requirements and standards set forth in Fairbanks North Star Borough (FNSB) Title 15 no later than 60 days after obtaining a finished construction elevation certificate or flood-proofing certificate, if required.
At a minimum, this will include an elevation certificate certifying the elevation of the lowest finished floor (including basement) of all new and substantially improved buildings; a report stating that the ability of the channel to adequately carry floodwater will be maintained at the same capacity as prior to alteration for watercourse alteration or relocation; a Zero Rise Certification for construction, fill or other development in a regulatory floodway.